Question 8
MediumOriginal questionA firm makes units of product M and of product N. Machine time is 3 h for M and 1 h for N, with 15 h available; labour is 1 h for M and 2 h for N, with 10 h available. Which constraints are right?
Show the answer and explanation
CorrectNot quiteAnswer B
Correct answer: B
Explanation
Write each resource as (amount used per unit) × (number of units), added over the products.
'At most' or 'available' gives ≤, 'at least' or 'must give' gives ≥; a profit is maximised and a cost minimised.
- Concept
- Constraints from two resources
- Typical timeTypical
- 90 s
- Your timeYours
- —