Question 46
MediumOriginal questionTwelve workers, working 8 hours a day, finish laying a road in 15 days. How many days will 18 workers take for the same job if they work 10 hours a day?
Show the answer and explanation
CorrectNot quiteAnswer A
Correct answer: A
Explanation
Total work = worker-hours.
18 workers × 10 hours = 180 worker-hours per day.
Days = .
Worth noting
10 days ignores the change in daily hours; 28.125 treats every quantity as directly proportional.
- Concept
- Workers × hours × days is constant for a fixed job
- Typical timeTypical
- 70 s
- Your timeYours
- —
Practise this chapter →