Question 51
HardOriginal questionTwenty workers can build a 240 m long boundary wall in 18 days. How many workers are needed to build a 400 m wall of the same kind in 15 days?
Show the answer and explanation
CorrectNot quiteAnswer C
Correct answer: C
Explanation
Work per metre = worker-days.
A 400 m wall needs worker-days.
In 15 days: workers.
Worth noting
24 ignores the longer wall ; 34 rounds up 33.3, which ignores the shorter time.