Question 41
HardOriginal questionA contractor plans to lay a road with 30 workers in 40 days. After 16 days, 10 more workers join. In how many days in all is the road finished?
Show the answer and explanation
CorrectNot quiteAnswer C
Correct answer: C
Explanation
Total work = worker-days.
In 16 days: worker-days, leaving 720.
Now 40 workers: more days.
Total = days.
Worth noting
18 days counts only the time after the new workers join. 30 days assumes all 40 workers were there from day 1.
- Concept
- Change in workforce midway: worker-days
- Typical timeTypical
- 120 s
- Your timeYours
- —
Practise this chapter →