Question 12
MediumOriginal questionRavi can repair a road stretch in 20 days and Sunita in 30 days. They work together for 6 days, after which Ravi is moved to another site and Sunita finishes the rest alone. How many days does the whole repair take?
Show the answer and explanation
CorrectNot quiteAnswer D
Correct answer: D
Explanation
Together they do per day.
In 6 days: of the road.
Sunita does the other at per day: days.
Total = days.
Worth noting
15 days is only Sunita's part; the question asks for the whole repair, so add the first 6 days.