Question 38
MediumOriginal questionA contractor estimates that 45 workers will finish a metro-station floor in 32 days. If he hires 60 workers instead, how many days earlier will the floor be finished?
Show the answer and explanation
CorrectNot quiteAnswer A
Correct answer: A
Explanation
Total work = worker-days.
With 60 workers: days.
Days saved = days.
Worth noting
24 days is the new time, not the saving. The question asks how many days EARLIER.
- Concept
- M₁D₁ = M₂D₂ applied to a time saving
- Typical timeTypical
- 70 s
- Your timeYours
- —