Time & Work · Question 38 of 61

Question 38

MediumOriginal question

A contractor estimates that 45 workers will finish a metro-station floor in 32 days. If he hires 60 workers instead, how many days earlier will the floor be finished?

Options for question 38

Show the answer and explanation
CorrectNot quiteAnswer A

Correct answer: A

Explanation

  1. Total work = 45×32=144045 \times 32 = 1440 worker-days.

  2. With 60 workers: 1440÷60=241440 \div 60 = 24 days.

  3. Days saved = 32−24=832 - 24 = 8 days.

Worth noting

24 days is the new time, not the saving. The question asks how many days EARLIER.

Concept
M₁D₁ = M₂D₂ applied to a time saving
Typical time
70 s