Time & Work · Question 24 of 61

Question 24

HardOriginal question

Two carpenters, Manoj and Rehana, can make a set of classroom benches together in 12 days. They work together for 5 days, then Rehana leaves and Manoj finishes the rest alone in 21 days. How many days would Rehana take to make the whole set alone?

Options for question 24

Show the answer and explanation
CorrectNot quiteAnswer A

Correct answer: A

Explanation

  1. In 5 days together: 512\frac{5}{12} done, leaving 712\frac{7}{12}.

  2. Manoj does 712\frac{7}{12} in 21 days, so his rate is 712÷21=136\frac{7}{12} \div 21 = \frac{1}{36} per day.

  3. Rehana's rate = 112−136=236=118\frac{1}{12} - \frac{1}{36} = \frac{2}{36} = \frac{1}{18}.

  4. Rehana alone takes 18 days.

Worth noting

36 days is Manoj's time, not Rehana's. 28 days comes from treating Manoj's 21 days as the whole job instead of the remaining seven-twelfths.

Concept
Deducing an individual rate from a two-phase job
Typical time
120 s
Your time
—
The rule this testsWork rate and working together